6 unit system is tested and with a load demand of 1263MW.
=== OPTIMIZATION RESULTS ===
Best Total Cost: $15699.94/hour
Power Generation (MW):
Plant 1: 450.03 MW
Plant 2: 177.71 MW
Plant 3: 264.64 MW
Plant 4: 150.00 MW
Plant 5: 160.58 MW
Plant 6: 91.47 MW
Constraint Verification:
Total Generation: 1294.42 MW
Transmission Losses: 31.42 MW
Net Power Supply: 1263.00 MW
Power Demand: 1263.00 MW
Power Balance Error: 0.0000 MW
Cite As
praveen kumar (2026). Application of LSHADE to Economic Dispatch Problem (https://uk.mathworks.com/matlabcentral/fileexchange/182137-application-of-lshade-to-economic-dispatch-problem), MATLAB Central File Exchange. Retrieved .
General Information
- Version 1.0.0 (4.96 KB)
MATLAB Release Compatibility
- Compatible with any release
Platform Compatibility
- Windows
- macOS
- Linux
| Version | Published | Release Notes | Action |
|---|---|---|---|
| 1.0.0 |